Sunday, January 20, 2013
New Year Project
Well we are continuing with our project. Sorry about failing to post during the fall period.
We completed the framing of the walls in the basement.
We completed the wiring and installation of 27 pot lights.
Everything has been inspected and passed.
Over Xmas period completed the drywall boarding.
We are 75% complete on the first coat of drywall mud.
Hope to be to paint stage by 1 Feb.
Then it is install flooring and trim getting ready to start the spare bedroom and bathroom in March, just in time to move back out doors and the back yard landscaping and garden making.
I must be very wicked as there does not appear to be any rest soon.
Friday, August 17, 2012
The Path To Our Doorway Is Paved In Cement..Sort Of
A few weeks ago, Bob came to help top up the insulation in the attic. Settling has happened over the past couple of years...I know the feeling. Anyway, while he was here, he also got roped into spreading gravel along the front of the house as landscaping continues.
Since then the spreading has continued...again, I know the feeling. Now that the gravel has been spread all along the front of the house, it's time to create a sidewalk.
Jim has hauled out the old, yet reliable, cement mixer and using forms that we bought for a decorative sidewalk, the pouring has begun.
Tuesday, July 10, 2012
Jim's New Toy...
Tuesday, July 3, 2012
The Saga of Summer Landscaping Continues..
Friday, May 18, 2012
If Mothers Can Have Anything They Want On Mothers Day...
...I wanted a fence. So, I was out there with Jim and the post pounder to surround the property with fence posts. 151, 7 foot long, 3 1/4" wooden posts were pounded in to a depth of 4 feet between Saturday May 12 and Sunday May 13 (Mothers Day). We still have 9 left but they couldn't be put in either because the post pounder couldn't be maneuvered into place or because the shed (which has to be moved) was in the way.
We will spend the summer purchasing and installing the 10 foot rails that connect the posts, a few at a time. For now, Ma and Pa Farrell are pooped.
We will spend the summer purchasing and installing the 10 foot rails that connect the posts, a few at a time. For now, Ma and Pa Farrell are pooped.
I'm So Treed Off!!
The old, cow pasture is pretty bald...devoid of anything taller than a weed. This is the year for basic surround trees. Yeppers, the fast growing Brooks #6 Poplar. We chose the male cultivar so we won't have to deal with all the fluff. In my over exuberance, I managed to buy 200 plugs...the roots are about 3-4 inches long and the tree is only a small stick. We only needed 75...oops. We ended up planting 90 as we thought we might need some replacement trees. Turned out we were right...those rotten pocket gophers have eaten 2 and one was run over by the truck while we were fencing...no not with sabres. Our neighbours gladly pitched in and gave homes to the remaining 110.
It Is Way Past Time For An Update On The Basement
All the electrical has been completed and poor Jim had to install 29 pot lights in the bulk heads of the rec room area, as well as, 2 other overhead lights.
As the framing is complete and the electrical, aside from the bathroom, is also done, we are at a standstill as the county has to inspect before we can go any farther. I applied for the development, electrical and plumbing permits 3 weeks ago and we are still waiting for approval. Until they are approved we can't call for an inspection. Oh well...it's spring and the yard awaits.
As the framing is complete and the electrical, aside from the bathroom, is also done, we are at a standstill as the county has to inspect before we can go any farther. I applied for the development, electrical and plumbing permits 3 weeks ago and we are still waiting for approval. Until they are approved we can't call for an inspection. Oh well...it's spring and the yard awaits.